Xylem Manufacturing Facility Renovation

Project Overview

T-Ross Brothers Construction completed a large-scale renovation and facility improvement project for Xylem’s manufacturing operations in Watsontown, Pennsylvania, upgrading the company’s main production plant and Bay #1.

The project encompassed approximately 21,600 square feet of active production space and included extensive structural, concrete, masonry, building envelope, lighting, and operational improvements designed to enhance the facility’s durability and long-term performance.

The Challenge

Completing extensive renovations within an active manufacturing environment required careful scheduling, safety planning, and coordination to minimize disruption to Xylem’s ongoing production operations.

The existing facility required significant demolition and structural modifications, including removal of exterior brick and foundation walls, interior framed wall systems, and raised floor areas within Bay #1. The project also required coordination of environmental demolition requirements and repairs to damaged portions of the existing structure.

Our Solution

T-Ross Brothers coordinated demolition, excavation, and construction of new foundations, reinforced concrete floor systems, masonry frost walls, and structural framing to support the updated manufacturing environment.

Significant building envelope improvements included new standing seam roofing, insulated metal wall panels, structural girts, and additional insulation systems designed to improve durability and building performance.

Operational and safety improvements included new overhead and hollow metal doors, fencing, LED lighting, emergency lighting, and exterior wall packs. Structural repairs were also completed and carefully integrated with the new construction throughout the existing facility.

The Results

Upon completion:

  • Approximately 21,600 square feet of manufacturing space renovated and improved

  • Extensive demolition and structural modifications completed

  • New foundations and reinforced concrete floor systems

  • New masonry frost walls and structural framing

  • New standing seam roofing system

  • Insulated metal wall panels and additional insulation

  • Structural repairs to damaged portions of the existing facility

  • New overhead and hollow metal doors

  • New fencing and operational improvements

  • Upgraded LED lighting throughout production areas

  • New emergency lighting and exterior wall packs

  • Building envelope improvements designed for increased durability and performance

  • New construction integrated with the existing manufacturing facility

  • Renovations carefully coordinated around active production operations

EXPERIENCE YOU CAN BUILD ON

More than 65 years of experience

Office:

2733 State Rt 45, Milton PA

Call:

(570) 524-6411

Site:

www.trossbrothers.com

© Copyright T-Ross Brothers Construction, Inc. 2026. All rights reserved.